Acceptance criteria for active partition wall

The inspection quantity of movable partition works should meet the following requirements: each inspection lot should be checked at least 20%, and not less than 6, and should be checked in full when less than 6.

Main control items: the varieties, specifications, performance and wood moisture content of wallboards, fittings and other materials used in movable partitions should meet the design requirements. If there are requirements for smoldering, moisture-proof and other characteristics, the test report of corresponding performance grade should be made.

Inspection method: observe, inspect product qualification certificate, entry acceptance record, performance test report and reinspection report.

The movable partition rail must be firmly connected with the base structure and should be positioned correctly.

Test method: scale examination; hand wrench examination.

The components and fittings used for assembly, push and pull and brake of the project activity partition must be installed firmly and correctly, and the push and pull must be safe, stable and flexible.

Inspection methods: ruler examination; hand pull examination; push pull inspection.

The production method and combination method of movable partition wall should meet the design requirements.

Test method: observation.

General project

The surface of movable partition should be uniform and smooth, and the clean line should be straight and clear.

Test method: observation; hand touch examination.

The holes, troughs and boxes on the movable partition should be positioned correctly, neatly cut, and neatly arranged.

Test method: observation; examination of scale.

The moving wall should be pushed and pulled without noise.

Test method: push and pull check.

The allowable deviation and inspection method for the installation of movable partitions shall comply with the requirements of table 7.4.10.